SECTION 02 / Do-it-yourself game plans

What should the internal team budget? Build from effort and quotes, not an invented market rate.

Runrate research deskSection 02Page 10 of 15Last updated 13 November 2026

For assessment planning only, a resource allowance is 15 project-lead days, five finance days, six operations days, six data/IT days, three legal/security days and three procurement days: 38 person-days. At an internal opportunity-cost rate of $800/day, that is $30,400, before external work or software. These are modelling assumptions to replace, not observed salaries or consulting fees.

Add external quotes, access/remediation costs and an explicitly justified contingency. Track time already spent separately from future cash commitments. If the internal team cannot supply the records, do not describe DIY as free; its missing capacity is a real project constraint.